Skip to main content
SIM GMB 2025 01 JANUARY 29 0884

CBD Sector Sewer Trunk Main

The construction of four new or upgraded wastewater trunk mains in the Mount Barker area is required to ensure the collection network has the required capacity to cater for growth. The trunk mains are needed to enable the provision of an essential public health service and to satisfy legal obligations entered into with a number of developers in the Mount Barker growth area to supply development sites with a sewer service.  The Nairne trunk sewer, completed in April 2025, was the first to be delivered followed by the Mount Barker CBD Sewer Trunk Main Project (nearing completion), and followed by the Central and Eastern Stage Two projects.

The CBD Sewer Trunk Main project is nearing the finish line, with most sections along the route completed and reopened.

Connection and commissioning works are now underway, as are minor defect rectification activities which may require temporary closures, and pedestrian detours may be in effect.

The temporary use of Dunn Park Oval as a laydown area has now finished, with all materials and equipment removed from the site.  The area has been tidied and reinstated, including levelling, applying topsoil, and hydroseeding to establish grass. Hydro-seeding has been applied to assist with dust suppression over the wetter months to give the new grass the est chance to establish. 

The Contractor responsible for installing the pipes as part of the Sewer Trunk Main Program of Works is BMD Construction, and they have appointed Andrea Shaw of CPR Communications to assist with community and stakeholder relations, and to keep directly impacted parties informed about the works.